The patent badge is an abbreviated version of the USPTO patent document. The patent badge does contain a link to the full patent document.

The patent badge is an abbreviated version of the USPTO patent document. The patent badge covers the following: Patent number, Date patent was issued, Date patent was filed, Title of the patent, Applicant, Inventor, Assignee, Attorney firm, Primary examiner, Assistant examiner, CPCs, and Abstract. The patent badge does contain a link to the full patent document (in Adobe Acrobat format, aka pdf). To download or print any patent click here.

Date of Patent:
Aug. 30, 2022

Filed:

Nov. 20, 2018
Applicant:

Vestas Wind Systems A/s, Aarhus N, DK;

Inventors:

Manoj Gupta, Singapore, SG;

Ravi Kumar, Melbourne, AU;

Janakiraman Sivasankaran, Singapore, SG;

Assignee:

VESTAS WIND SYSTEMS A/S, Aarhus N, DK;

Attorney:
Primary Examiner:
Int. Cl.
CPC ...
H02J 3/46 (2006.01); H02J 3/32 (2006.01); H02J 13/00 (2006.01); G05B 15/02 (2006.01); H02J 3/38 (2006.01);
U.S. Cl.
CPC ...
H02J 3/32 (2013.01); G05B 15/02 (2013.01); H02J 3/381 (2013.01); H02J 3/46 (2013.01); H02J 13/00002 (2020.01); H02J 2300/20 (2020.01); H02J 2300/24 (2020.01); H02J 2300/28 (2020.01);
Abstract

A method of controlling a hybrid power plant connected to a power network, the hybrid power plant having a first renewable energy generator and a second renewable energy generator, the first renewable energy generator being configured to generate power using a different source of renewable energy to the second renewable energy generator. The method comprises: determining a target plant power output for the hybrid power plant; determining a target generator power output for each of the first and second generators based on the target plant power output; determining a respective ramp rate for each of the first and second renewable energy generators based, at least in part, on an attribute of the respective renewable energy generator; and operating each of the first and second renewable energy generators to change its power output to the power network at the determined ramp rate to achieve the target generator power output.