The patent badge is an abbreviated version of the USPTO patent document. The patent badge does contain a link to the full patent document.

The patent badge is an abbreviated version of the USPTO patent document. The patent badge covers the following: Patent number, Date patent was issued, Date patent was filed, Title of the patent, Applicant, Inventor, Assignee, Attorney firm, Primary examiner, Assistant examiner, CPCs, and Abstract. The patent badge does contain a link to the full patent document (in Adobe Acrobat format, aka pdf). To download or print any patent click here.

Date of Patent:
Jun. 29, 2021

Filed:

Dec. 25, 2018
Applicant:

Shandong University of Science and Technology, Qingdao, CN;

Inventors:

Shaojie Chen, Qingdao, CN;

Zhaowen Du, Qingdao, CN;

Zhiguo Xia, Qingdao, CN;

Zhen Zhang, Qingdao, CN;

Bing Chen, Qingdao, CN;

Zhiyuan Li, Qingdao, CN;

Yong Jian, Qingdao, CN;

Attorney:
Primary Examiner:
Int. Cl.
CPC ...
E21F 15/08 (2006.01); E21C 41/18 (2006.01); E21F 15/02 (2006.01);
U.S. Cl.
CPC ...
E21F 15/08 (2013.01); E21C 41/18 (2013.01); E21F 15/02 (2013.01);
Abstract

Provided is a filling mining method for a fully-mechanized top coal caving working face, which relates to the field of mining engineering technologies. The method solves the technical problems of roof control of the fully-mechanized top coal caving working face and a large ground deformation of top coal caving mining. The method includes the following steps: at step A, dividing the fully-mechanized top coal caving working face into a filling zone and a top coal caving zone along a strike of the working face, or dividing the working face into a filling zone and a top coal caving zone along a strike and an inclination of the working face; at step B, determining a cycle interval of the working face; at step C, performing supporting for the filling zone before the working face, and completing coal caving in the top coal caving zone and performing round wood supporting in the filling zone; at step D, after the filling zone reaches the filling interval, disposing a filling tarpaulin behind a hydraulic support and pumping the filling paste; at step E, repeating steps C and D to complete mining. A mining method of alternate coal caving and filling is provided to complete the filling mining of the top coal caving working face. In this way, the roof is effectively controlled, ground subsidence is reduced and advantages such as safety and high efficiency are available.